    Primavera (EPPM) how to filter activities with particular resource assigned

    2 replies [Last post]
    Chary Chary
    User offline. Last seen 2 weeks 2 days ago. Offline
    Joined: 6 Apr 2016
    Posts: 12
    Groups: None

    Dear all,

    I am just trying to find a way to do what is quite simply done in Ms Project: to filter activities, which have a particular resource assigned to them.

    The only way I found is to go to assignments and to create a filter, which filters assignments based on a project.

    Is there a way to do it out of Activities?

    Replies

    Zoltan Palffy
    User offline. Last seen 1 day 23 hours ago. Offline
    Joined: 13 Jul 2009
    Posts: 2592
    Groups: None

    yes 

    filter 

    where resource name equals what ever the resource name is 

    Santosh Bhat
    User offline. Last seen 6 hours 39 min ago. Offline
    Joined: 15 Apr 2005
    Posts: 250

    Look in the Reource Assignments view rather than in the Activities View.