    Rogue Activity in P6 program

    5 replies [Last post]
    Alan Dunn
    User offline. Last seen 1 week 5 days ago. Offline
    Joined: 21 Dec 2009
    Posts: 13

    Hi all,

    I am a frustrated P6 V18 user and have an intiguing issue at the moment.  In one of my programs which I inherited from another planner I have an activity doing something very strange.  Activities were loaded with resources reflecting the revenue/claim value for the project for the activity.  Some of these involve LOEs for indirects.  In one of these activities the Remaining Units/Time and thus the Remaining Units double every time I choose to reschedule leading to an exponential error.  There is nothing particularly uniique about this activity as there are others like it in the program that are not behaving like this.  Has anybody else had an issue like this?

    Replies

    Zoltan Palffy
    User offline. Last seen 1 day 23 hours ago. Offline
    Joined: 13 Jul 2009
    Posts: 2592
    Groups: None

    glad I could help you.

    Finding the anomolies and what is common among the activities that are casuing problems is always a good way to find the root of the problem.

    Alan Dunn
    User offline. Last seen 1 week 5 days ago. Offline
    Joined: 21 Dec 2009
    Posts: 13

    Thanks Zoltan for the reply.  All the logic is fine.  There is however a difference in the Curve settings.  Interestingly the problem activity is the only one with a curve assigned (linear).  When I removed this selection the problem resolved itself.....

    Alan Dunn
    User offline. Last seen 1 week 5 days ago. Offline
    Joined: 21 Dec 2009
    Posts: 13

    Thanks David,  I could delete & re-add, but as I rarely get data issues with P6 I like to know what is happening and why.

    Zoltan Palffy
    User offline. Last seen 1 day 23 hours ago. Offline
    Joined: 13 Jul 2009
    Posts: 2592
    Groups: None

    try to look for the anomoily for this activity see whats is commom among these activiites 

    if it is a LOE it wil be geeting the actauls from the activities that it is summarizing.

    a LOE should have a SS predcessor and a FF successor

    also a LOE should have a curve assigned to it or it will stack all of the resources on the data date

    David Kelly
    User offline. Last seen 1 day 22 hours ago. Offline
    Joined: 19 Oct 2004
    Posts: 577
    Alan, Never. Have you tried delete and re-add?