    Transfer Progress between 2 Programmes

    4 replies [Last post]
    Mike planner
    User offline. Last seen 1 week 3 days ago. Offline
    Joined: 3 Feb 2011
    Posts: 41
    Groups: None

    Hello All, 

     

    I have progresss a programme and added some new activities as Rev 08, progressed as at 14-Feb-20 

    However, my previous progress is Rev 07, which was progressed on the 17-Jan-20. 

    Can i know if there is a quick method that i can transfer my progress from Rev 08 to Rev 07a? 

     

    Many thanks

    Mike 

    Replies

    Zoltan Palffy
    User offline. Last seen 1 day 23 hours ago. Offline
    Joined: 13 Jul 2009
    Posts: 2592
    Groups: None

    open Rev 8 and make rev 7 a baseline

    then select maintain baselines and select update

    then from here you can choose what to update all activities or a filter or additional update options under Update options 

    pick and choose what to update 

    when you are done select Restore to put REV7 back into the selectable projects

    Alexandre Faulx-B...
    User offline. Last seen 1 day 19 hours ago. Offline
    Joined: 20 Jan 2003
    Posts: 1278

    Hello Mike,

    I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6

    Alexandre

    Mike planner
    User offline. Last seen 1 week 3 days ago. Offline
    Joined: 3 Feb 2011
    Posts: 41
    Groups: None

    Hmnn... not that easy, because i have changed some duration and logic. 

    I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another 

     

    Many thanks

    Mike 

    Santosh Bhat
    User offline. Last seen 6 hours 38 min ago. Offline
    Joined: 15 Apr 2005
    Posts: 250

    Don't you just make a copy of Rev 08 and then delete the new activities?