    Price/ Unit - Budget Cost

    7 replies [Last post]
    Haresh Jayanth
    User offline. Last seen 2 years 1 week ago. Offline
    Joined: 24 Aug 2006
    Posts: 219
    Primavera is calculating Budgeted Cost by following equation , w.r.t Price / Unit.
    For example:

    a) Price / Unit: $120 /d
    b) Suppose Duration of the activity is 10 days.
    c) Budgeted cost is shown as $ 150 instead of $ 1200, which means primavera is calculating Budget cost based on the following formula i.e.

    (120 / 8) (No of working hours in a day) * 10 (duration)= $150.

    But it take this formula: 120 * 10days = $1200, why this is happening??? Kindly advice.....

    Replies

    Zoltan Palffy
    User offline. Last seen 1 day 23 hours ago. Offline
    Joined: 13 Jul 2009
    Posts: 2592
    Groups: None

    view show on bottom resource usage profile 

    then click the cost box 

    Russ Tomb
    User offline. Last seen 1 week 6 days ago. Offline
    Joined: 10 Feb 2020
    Posts: 11
    Groups: None

    Hi! I am newbie with this type of program and career line.

     

    Please enlighten me with resources. They gave me a file with indicated budget for each activity and I need to make an s-curve using p6.

     

    Is this possible?

     

    Ex.

    Activity ID Activity Name Orig Duration Start Finish   

       A1020     Excavation            180 05-Jan-19 03-Jul-19
    Rodel Marasigan
    User offline. Last seen 39 weeks 2 days ago. Offline
    Joined: 25 Oct 2006
    Posts: 1516
    Haresh,
    This is common if you modify your resource rate or change something which is also affected by duration type setting. If both prices assigned to resource and activity detail, resource tab are the same then try this.
    Tools-> Recalculate assigment Cost. That should fixed the problem.

    Note: Things that needs to check
    1) Edit-> User Preferences-> Time Units tab-> Unit Format (is it hour or day?)
    2) Resource max unit/time = (8/day or 10/day)
    3) Resource Price/ Unit = ($?/h or $?/d)
    4) Activity Window-> Resource tab-> Budget Unit = ?
    5) Activity Window-> Resource tab-> Price/unit = ($?/h or $?/d)
    Irfan Khan
    User offline. Last seen 8 weeks 23 hours ago. Offline
    Joined: 19 Jul 2009
    Posts: 138
    Hi,

    Joel is correct refresh ur data or check ur Admin Preferences may be something wrong there......!

    regards,,,,,

    Joel Villanueva
    User offline. Last seen 7 years 51 weeks ago. Offline
    Joined: 7 Mar 2010
    Posts: 21
    Haresh,

    Anyway, just try to re-schedule and refresh data sometimes it displays wrong output if you did some editing of data without refreshing and or re-scheduling.

    Regards,
    Joel
    Haresh Jayanth
    User offline. Last seen 2 years 1 week ago. Offline
    Joined: 24 Aug 2006
    Posts: 219
    Dear Mr. Joel,

    Both prices assigned to resource and activity detail, resource tab are the same.

    But still the problem persists

    regards,

    Haresh
    Joel Villanueva
    User offline. Last seen 7 years 51 weeks ago. Offline
    Joined: 7 Mar 2010
    Posts: 21
    Hi Haresh,

    Check if your price/unit under “Activity details” resources column is the same with your price/unit assigned under “Resources window” if not, re-schedule the program and click refresh data under “File menu”.

    Regards,
    Joel